BEFORE THE BOARD OF
SUPERVISORS OF LIBERTY TOWNSHIP, ADAMS
COUNTY, PENNSYLVANIA
In re: Application
of Liberty Development Company, LLC, for
approval of a tentative plan for a planned
residential development known as "Liberty
Valley"
I. BACKGROUND
A. Planned
Residential Districts in Liberty Township.
Liberty Township has
a Zoning Ordinance (hereinafter "ZO") that
was adopted on April 3, 1984. The ZO has
been amended at least twice since its
adoption in 1984. Of particular concern to
the application by Liberty Development
Company, LLC (hereinafter "applicant") was
an amendment dated May 7th, 1985, which
repealed "all special uses under the zoning
ordinance of Liberty Township. Specifically
sections 3.1 (B), 3.2 (C) and 3.3 (B) of the
Liberty Township Ordinances will be repealed
by this ordinance."
Prior to the
amending ordinance of 1985, planned
residential developments (hereinafter "PRD")
were permitted only in the General Use
district as a "special use". The Board of
Supervisors of Liberty Township (hereinafter
"Board") believes it was the intent of the
Supervisors holding office in 1985 to
eliminate planned residential developments
from the Township's zoning scheme. However,
the article of the ZO that prescribes the
details of PRDs was not repealed, and
existed as part of the ZO until repealed on
February 3, 2004.
The Board concludes
that PRDs were eliminated from the Township,
but due to an error in not repealing Article
V of the ZO, a claim could be, and has been,
made that PRDs are now permitted everywhere
in the Township. The applicant claims that
the failure to remove Article V of the ZO at
the time that the PRD use was "repealed" by
the 1985 ordinance shows an intent on the
part of the Township to allow PRDs in all
parts of the Township. Applicant cites Doran
Investments v. Muhlenberg Township, 10
Pa.Cmwlth. 143, 309 A.2d 450 (1973) as
support for that claim.
Doran is not
apposite factually to the Liberty Township
situation. In Doran, Muhlenberg Township
apparently added PRDs to its zoning scheme
after zoning had already been put into
place. The additions of PRDs was by a
separate ordinance (named "Ordinance 106"),
and may have specifically stated that it was
applicable throughout the township. ("A few
months subsequent to Village 2 at New Hope,
the Legislature passed Article VII of the
MPC which permits municipalities to adopt
ordinances allowing for "planned residential
developments" with a mix of types of
residential uses and of some commercial uses
on a single tract, in specific locations, as
in Village 2 at New Hope or, as the
Muhlenberg Ordinance, 106 provides, anywhere
in the municipality." [underlining added for
emphasis]. 309 A.2d at 454.) Liberty
Township, on the other hand, had provided
for PRDs at one location only (the GU
district) and then repealed that
designation. Unlike Muhlenberg Township that
was adding the PRD use to its zoning scheme,
Liberty was repealing existing "special
uses". Liberty's action was the antithesis
of a wider application of PRD opportunities
in the Township.
The Board concludes
that the Liberty Valley application is
improper and is, therefore, denied on the
basis that PRDs are not uses allowed in
Liberty Township. However, since the
applicant's claim (that the failure to
repeal Article V caused PRDs to be retained)
might be found to be valid, the Board
allowed the applicant to proceed with its
application. (The Board feels it was
compelled to hold the hearings due to the
"deemed approval" language of the MPC. If a
court concluded that PRDs were not removed
from Liberty Township, but no hearings held
been held within 180 days after the filing
of the application, the application would
have been deemed to have been approved. MPC
§ 709(a). ) The balance of this decision has
been prepared and adopted in the event that
a court, by a final order, declares that
PRDs were valid in Liberty Township at the
time that the application was filed.
B. Interplay between
the Municipalities Planning Code and the ZO.
The application
filed by the applicant is a request for
tentative plan approval for a PRD. The
procedures for tentative plan approval and
review are prescribed by both the
Municipalities Planning Code, found in 53
P.S. §10101, et seq, as amended (hereinafter
"MPC") and by the ZO. The procedural
provisions of the ZO addressing tentative
plans are found in sections 5.8 A. through
5.8 E. Requirements of the Township's
Subdivision and Land Development Ordinance
(Ordinance of March 18, 1992) (hereinafter "SALDO")
are incorporated into Article V of the ZO by
sections such as ZO §§ 5.5 D, 5.8 A., and
5.8 B.
At the hearings held
on the application, there were recurring
discussions about whether the application
was complete. It was the position of at
least one of the protestants that the
tentative plan application was not complete
as it did not contain everything required of
a preliminary plan that might be filed for
subdivision and/or land development review
and approval. This position seems to have
been based on one or both of the following
two ZO sections:
A. The application
for tentative approval shall be submitted by
or on behalf of the land owner to the
Township Secretary in accordance with the
requirements of the Township Subdivision and
Land Development Ordinance.
B. The application
for tentative approval shall in addition to
the plans and supporting data required in
the Subdivision and Land Development
Ordinance and this Article contain the
following: [then providing certain
requirements similar to some of those
provided in MPC § 707 (4)(i - ix)].
ZO, §§ 5.8. A. & B.
The MPC provides, in
pertinent part
Application for
Tentative Approval of Planned Residential
Development. In order to provide an
expeditious method for processing a
development plan for a planned residential
development under the provisions adopted
pursuant to the powers granted herein, and
to avoid the delay and uncertainty which
would arise if it were necessary to secure
approval, by a multiplicity of local
procedures, of a plat of subdivision as well
as approval of a change in the zoning
regulations otherwise applicable to the
property, it is hereby declared to be in the
public interest that all procedures with
respect to approval or disapproval of a
development plan for a planned residential
development and the continuing
administration thereof shall be consistent
with following provisions:
* * *
(4) The provisions
shall require only such information in the
application as is reasonably necessary to
disclose to the governing body …
(i) the location,
size and topography of the site and the
nature of the landowner's interest in the
land proposed to be developed;
(ii) the density of
land use to be allocated to parts of the
site to be developed;
(iii) the location
and size of the common open space and the
form of organization proposed to own and
maintain the common open space;
(iv) the use and the
approximate height, bulk and location of
buildings and other structures;
(v) the feasibility
of proposals for water supply and the
disposition of sanitary waste and storm
water;
(vi) the substance
of covenants, grants of easements or other
restrictions proposed to be imposed upon the
use of the land, buildings and structures
including proposed easements or grants for
public utilities;
(vii) the provisions
for parking of vehicles and the location and
width of proposed streets and public ways;
(viii) the required
modifications in the municipal land use
regulations otherwise applicable to the
subject property;
(viii.1) the
feasibility of proposals for energy
conservation and the effective utilization
of renewable energy sources; and
(ix) in the case of
development plans which call for development
over a period of years, a schedule showing
the proposed times within which applications
for final approval of all sections of the
planned residential development are intended
to be filed and this schedule must be
updated annually, on the anniversary of its
approval, until the development is completed
and accepted.
(6) The application
for and tentative and final approval of a
development plan for a planned residential
development prescribed in this article shall
be in lieu of all other procedures or
approvals, otherwise required pursuant to
Articles V and VI of this act.
53 P.S. §§ 10707
(4), 10707(6) [underlining added for
emphasis]
In case of conflict
between a municipal ordinance, and the MPC,
the MPC controls. 53 P.S. § 10103. When the
words of a statute are clear and free from
all ambiguity, the letter of it is not to be
disregarded under the pretext of pursuing
its spirit. 1 Pa.C.S. § 1921(b). Words are
to be construed according to their common
and approved usage. 1 Pa.C.S. § 1903(a).
"Shall" denotes a mandatory, not a
permissive, instruction. Cranberry Park
Assoc., L.P. v. Cranberry Tp. Z.H.B., 561
Pa. 456, 751 A.2d 165 (2000).
Municipal
governments have only those powers expressly
given or necessarily implied in grants of
power from the Legislature. Appeal of
Galgliardi, 401 Pa. 141, 163 A.2d 418
(1960). Any fair, reasonable doubt as to the
existence of a power in a municipality is
resolved by the courts against its
existence. Knauer v. Commonwealth, 17
Pa.Cmwlth. 360, 332 A.2d 589 (1975).
The Board concludes,
based on the statutory language and the
required interpretation of it, that the
application need only show those items set
out in the MPC. Any provisions of the ZO
that require more be shown in the
application than that provided in the MPC
are inconsistent with the MPC and are not
enforceable. An application that meets all
of the requirements of a preliminary
subdivision or land development plan would
contain much more than that contemplated by
the Legislature in a tentative plan
application. Such a plan submission would
not "avoid the delay … which would arise if
it were necessary to secure approval … of a
plat of subdivision … ." It should be noted,
however, that a duty falls on the applicant
to identify the "required modifications in
the municipal land use regulations otherwise
applicable to the subject property". As part
of this decision, the Board finds that any
applicable ZO or SALDO regulation for which
no modification has been requested (with the
exception of those regulations specifically
replaced by the spatial, density and use
provisions of Article V of the ZO) are
deemed to be applicable. Indeed, the bulk of
SALDO is applicable to these types of
project, and compliance therewith would be
mandatory at final plan stage(s). Bd. of
Supervisors of Charlestown Tp. v. West
Chestnut Realty Corp., 110 Pa.Cmwlth. 481,
532 A.2d 942 (1986).
C. Application and
Hearings. The application was filed on
September 29, 2003. Thereafter, a supplement
to the application was filed on or after
November 5, 2003. Pursuant to the MPC, the
first hearing was scheduled to commence
within 60 days after the filing of the
application. That first hearing was held on
November 24, 2003. All of the hearings were
held at the Fairfield Fire Company
facilities, 106 Steelman Street, Fairfield,
PA, and unless otherwise noted, each hearing
began at 6:30 p.m. and ended on or about
11:00 p.m. The second hearing was held on
December 9, 2003; the third hearing was held
on December 15, 2003; the fourth hearing was
held on December 17, 2003; the fifth hearing
was held on December 22, 2003; the sixth
hearing was held on January 14, 2004; the
seventh hearing was held in two sessions on
January 19, 2004, with one beginning at 4:00
p.m. and ending at 5:30 p.m., and the second
session beginning at 6:30 p.m. and ending at
approximately 10:50 p.m.; and the eighth and
last hearing was held on January 21 to
January 22, 2004, beginning at 6:30 p.m. and
ending at 1:06 a.m. on the 22nd. All of the
hearings were stenographically recorded by
Rhonda Kershner, except for the last hearing
which was recorded by Corrie Ondrizek. The
applicant was represented by the law firm of
Mette, Evans & Woodside in the persons of
Charles B. Zwally and James M. Strong,
Esquires. An unincorporated association
known as Save Our Liberty (also known as
"SOL") was recognized as a party. SOL was
represented by Reager & Adler, P.C. in the
person of Susan J. Smith, Esquire. Ms. Smith
also represented the following land owners
who were recognized as parties: John Tomko;
Charlene Tomko; Catherine Valentine; John
Milton; Faith Milton; George F. Kramer;
Karen Kramer; Joseph Marcharsky; Kellie
Marcharsky; Richard Swiat; Susan Swiat;
George P. Kramer; Linda S. Knox; Gene
Valentine; Clyde Wenschhof, Jr.; Nancy
Wenschhof; Robert Troxell; Patti Troxell;
and Ruppert Farm Limited Partnership. Also
recognized as parties, but appearing pro se
were: Mr. and Mrs. Geoffrey Ruppert; Mr. and
Mrs. David Goetz; and Mid-Atlantic Soaring
Association (by James Trygg).
D. Agreement for
Extended Decision Time. The MPC provides
that the Board has sixty (60) days after the
last hearing to render its decision. The ZO
provides that the Board has only thirty (30)
days to make such a decision. The applicant
offered, and all parties in attendance at
the end of the last hearing agreed, that the
time period for a decision by the Board
could be extended to the sixtieth (60th)
after the last hearing so that parties can
submit post hearing documents. It was
further agreed that: 1.any party wishing to
submit a memorandum of law, and/or proposed
findings of fact and conclusions of law, may
do so on or before Monday, February 23,
2004; and, 2.any party wishing to file a
reply memorandum of law shall do so on or
before Monday, March 1, 2004.
II. FINDINGS OF FACT
Facts used by the Board of Supervisors in
making its decision on this application are
found in the following FINDINGS OF FACT, and
in the text found in the portion of the
Decision labeled DISCUSSION. Both portions
of the Decision must be utilized for the
facts underlying the decision.
- On September 29,
2003, Liberty Development Company, LLC
filed with the Board of Supervisors of
Liberty Township an application for
approval of a tentative plan for a Planned
Residential Development known as Liberty
Valley (the "Liberty Valley PRD"). The
filing made on September 29, 2003 included
the following: (a) a transmittal letter;
(b) an application form required by the
Township Planning Commission; (c) a set of
plans containing 30 sheets; and, (d) a
bound volume entitled "Supplementary
Data".
- Following receipt
of a letter containing a "completeness
review" by the Township Engineer, the
applicant filed several additional items
including the following: (a) a transmittal
letter dated November 5, 2003; (b) a
revised set of plans containing 32 sheets;
and, (c) a bound volume entitled "Addendum
to Supplementary Data". The items filed on
September 29, 2003 and the supplemental
items filed on November 5, 2003 were
introduced into evidence as applicant's
Exhibit 1.
- The proposed
Liberty Valley PRD consists of three
contiguous parcels of land, one owned by
Donald S. Dawson, Trustee, identified as
Tax Map Parcel D-17-15, and the others by
Robert D. and Margaret S. Peloquin,
identified as Tax Map Parcel D-17-5 and
D-17-37.
- The Zoning
Ordinance requires a proposed planned
residential development to contain a
minimum of twenty (20) acres of land. ZO,
§ 5.2(A)(2). The proposed Liberty Valley
PRD contains approximately 444.70 acres of
land.
- The applicant is
the equitable owner of all of the parcels
included in the proposed Liberty Valley
PRD. The applicant has received written
authorization from the legal owners of the
parcels of land within the Liberty Valley
PRD, granting applicant authority to file,
inter alia, the tentative plan for
approval.
- The applicant
also proposes to develop a noncontiguous
adjacent tract of land containing
approximately 265 acres as a residential
subdivision known as "Liberty Estates" to
contain approximately 106 residential
lots.
- The proposed
Liberty Valley PRD is a separate project
from the proposed Liberty Estates
subdivision, but the two projects will
share a common owners association, as well
as a centralized water supply and sewer
system.
- The applicant has
established a nonprofit owners
association, identified as the Liberty
Valley and Estates Owners Association (the
"Owners Association"), which will be
composed of commercial and residential
owners in both the Liberty Valley PRD and
the Liberty Estates subdivision, will
initially be governed by the applicant as
the developer, and then as sales progress
control will be transferred to the owners.
- The centralized
water supply and sewer system are
anticipated to be owned and operated by a
public utility company to be formed by the
applicant or by the Owners Association.
- Additionally, the
Owners Association is expected to be
responsible for the proposed equestrian
center and clubhouse and maintenance of
parks and common areas not accepted by the
Township.
- The applicant has
also offered to the Fairfield Fire
Company, a one-acre parcel within the
proposed Liberty Valley PRD to be used by
the Fire Company for construction of a
fire and EMS substation and a $250
contribution from each sale of a dwelling
unit to help fund the Fire Company's
services.
- The applicant
submitted a market analysis with the
Tentative plan, which estimated potential
market demand for various types of housing
in the area of the proposed Liberty Valley
PRD. ZO, § 5.4(B).
- The applicant's
market analysis based its experience on
sales at Worman's Mill, Frederick County,
Maryland, and the Links at Gettysburg,
Adams County, Pennsylvania. The market
analysis also surveyed other nearby
projects including Hanover, Pennsylvania,
Taneytown, Maryland, and two within the
Emmitsburg, Maryland area.
- The market
analysis concludes that a percentage of
Liberty Valley PRD would be designed for
so-called "empty nesters" comprised of
active adults, 55 and older without
live-in children who seek first floor
master bedroom homes including single
family condominiums and townhouses. Other
homes will service the middle portion of
the population with housing products
ranging from townhouses for couples,
singles and smaller size families to large
estate homes on large single family lots.
- The applicant's
market analysis included a determination
that the project could support the
commercial uses contemplated in the plan
and described as a village center (the
"Village Center").
- The Liberty
Valley PRD is a community that anticipates
pedestrian travel, through the use of
sidewalks and trails, between residential
areas throughout the proposed community,
and the Village Center, but is not deigned
to facilitate maximum pedestrian use.
- The Liberty
Valley PRD incorporates a buffer zone
between the residential properties and
neighboring agricultural properties,
including an equestrian trail and then a
30-foot-wide strip to buffer the
properties. The outer boundaries of the
buffer will be designated using existing
fences or by placing markers. The existing
fences are not sufficient to contain the
uses planned without causing conflict with
existing neighboring uses.
- In designing the
Liberty Valley PRD, the applicant
recognized the existence of the
Mid-Atlantic Soaring Association (M-ASA)
facility and placed the lower density
units and the equestrian fields in that
area of the project in proximity to the
facility.
- Areas of Liberty
Valley PRD consist of "prime agricultural
soils".
- The proposed
Liberty Valley PRD consists of three
housing styles including single family
detached units, attached single family
units, and multiple family units.
- Each type of
housing style proposed for the Liberty
Valley PRD constitutes a minimum of 20% of
the total number of residential units
proposed for the Liberty Valley PRD.
- The residential
uses were not designed in accordance with
the site design requirements of the ZO, as
some units are closer than 20 feet to a
collector street. (See, townhouses facing
Tract Road in Phase 5). Pedestrian usage
is not promoted with regard to access to
common open space. (See, Discussion,
below).
- The proposed
Liberty Valley PRD includes a centrally
located retail/commercial area in the
Village Center, which is a single
concentrated area within the plan that has
access to Tract Road, a major collector
street.
- The proposed
commercial area was designed and intended
primarily to serve residents of the
proposed Liberty Valley PRD.
- The proposed
commercial center does not fit
harmoniously and compatibly into the
unitary design of the PRD. It "turns its
back" on the PRD by exposing the rear of
all the commercial buildings and views of
the expansive parking lots surrounding
those buildings to houses which face the
village center and passersby on adjacent
roads.
- The proposed area
for commercial use in the Liberty Valley
PRD is 8.21 acres, or 1.9% of the total
site area, which is less than the 6%
maximum permitted area for commercial use
for a project that exceeds 250 acres in
total site area.
- The maximum
permitted average gross residential
density is twelve (12) dwelling units per
acre. The Liberty Valley PRD proposes an
average gross residential density of 2.66
dwelling units per acre.
- The Zoning
Ordinance requires that at least 25% of
the total site area be devoted to common
open space. The common open space in the
proposed PRD contains storm water
management facilities of unknown area. The
applicant has failed to prove that the
amount of open space provided, after the
deduction of the area of the storm water
management facilities, meets the minimum
requirement.
- The Zoning
Ordinance provides that the maximum
permitted impervious coverage is not to
exceed 30% of the total site area and the
Liberty Valley PRD proposes a maximum
impervious coverage of 118.7 acres, or
26.7% of the total site area.
- The Zoning
Ordinance provides that the maximum
permitted lot coverage for commercial
buildings is not to exceed 25% of the
site's area designated for commercial use.
The Liberty Valley PRD proposes 1.84 acres
of commercial building lot coverage or
22.4% of the land area designated for
commercial use.
- The applicant had
requested certain waivers/modifications
with respect to requirements of the
Subdivision Ordinance. The
waiver/modification requests are set forth
in the Supplementary Data at Section 7
(Ex. A-1). The waivers/modifications
requested and the applicable sections of
the Subdivision Ordinance are as follows:
1)Section 402.3 with respect to minimum
street widths for one-way alleys;
2)Section 402.10.c applicable to maximum
length of a cul-de-sac; applicant requests
increase from 500 feet to 800 feet
maximum; 3)Section 301.2 Sheet Size -
requesting use of standard 24" by 36" size
sheet since print paper is not available
in required sizes; 4)Section 302.1.e. Key
Map Scale - requesting a smaller scale in
order to fit plan on one sheet; 5)Section
302.1.h. Contour Interval - requesting use
of 5' contours; 6)Section 302.2.d.
Preliminary Design of Bridges and
Culverts; 7)Section 302.2.i. Erosion and
Sedimentation Control Plan - requesting
deferral of adequacy letter from Adams
County Conservation District and NPDES
Permit from Pennsylvania Department of
Environmental Protection until final plan.
- Several of the
requested waiver/modifications were
favorably recommended by the Adams County
Office of Planning and Development; items
1, 2, and 4 above. In addition, the
waivers/modifications in items 5 and 6
above, relating to contour intervals and
preliminary design of bridges and
culverts, were no longer necessary and
effectively withdrawn following the filing
of the Addendum to Supplementary Data by
the applicant in response to the Township
Engineer's completeness review.
- The proposed PRD
shows housing units and roadways being
constructed in delineated wetlands. (See,
Discussion, below.)
- The Supplemental
Data to the proposed Liberty Valley PRD
contains a storm water drainage plan that
analyzed the amount of storm water runoff
the project would generate. The plan
provides for the amount of storage
necessary to control this runoff, in
compliance with the Township Ordinance,
through storm water ponds and additional
facilities, which would be used to control
the volumes, peak runoff and concentration
before the storm water leaves the
property. It appears that the storm water
ponds will need to be extremely deep in
order to contain the projected storm water
runoff, perhaps as deep as 17 feet. No
fencing around such deep ponds has been
shown, and the ponds could present a
danger and a hazard to the inhabitants of
the PRD.
- The applicant
provided the Township with a Natural
Features Analysis.
- The Tentative
plan does not show crosswalks at
intersections. The applicant indicates
that it will place crosswalks in the
vicinity of the commercial area, but no
other location is slated for crosswalks,
even though the PRD is to promote
pedestrian usage.
- The site plan for
the proposed Liberty Valley PRD delineates
areas of mature trees, which includes
trees that are six inches in diameter or
larger as determined by site survey and
were a factor in the placement of open
space and structures.
- The applicant
submitted a Traffic Assessment Report
prepared by Mark Metil, P.E. of Gannett
Fleming, which analyzed the potential
effects of the Liberty Valley PRD upon
intersections. The Report did not analyze
the effect of the PRD on the Township's
roadway systems, such as the current road
widths, shoulders, etc.
- The Traffic
Assessment Report called for data from six
intersections including: (1)Tract and
Wenchoff/Crum Roads; (2) Tract and Pecher
Roads; (3) Middle Creek and Pumping
Station Roads; (4) Pecher/Topper and Crum/Steelman
Marker Roads; (5) SR 16 and Steelman
Marker Road; and (6) Maryland Route 140
and Tract Road.
- The applicant's
Traffic Assessment Report predicts the
anticipated trip distribution of traffic
from the development from the start of
occupancy to full occupancy (years 2006
and 2021), with a gravity model, which is
based upon population employment centers
surrounding the study area, and the
distance those centers are from the study
area, to extrapolate a distribution
percentage of where people will travel.
This data included anticipated traffic
from the adjoining project, the Liberty
Estates subdivision.
- The Traffic
Assessment Report concluded that the
addition of trips from the Liberty Valley
PRD would have minimal impact on the
intersections identified in the study
area, due to the current lower traffic
volumes that now exist, and that only the
intersection at Tract Road and Route 140
in Maryland would require any
signalization improvements toward the end
of the project schedule. No proposals or
suggestions regarding the implementation
of traffic signals was provided.
- In 1992, when the
Comprehensive Plan for Liberty Township
was prepared, the number of daily trips on
Route 16, an arterial road in the
Township, had a trip usage of
approximately 5,023 trips per day.
- The applicant's
traffic expert testified that the
estimated total two-way trip generation
for the proposed Liberty Valley PRD would
be 1,208 trips during the a.m. peak hour
and 1,260 trips during the p.m. peak hour,
and these numbers are generally ten (10%)
percent of the daily traffic volume. The
total traffic to be generated by the
proposed PRD would then be calculated to
be between 12,080 and 12,600 trips per
day.
- The applicant
considered the width of existing Township
roads, including the availability of
shoulders, only in analyzing the capacity
of the roadways to provide volume to the
intersections studied. The applicant did
not include any information or analysis of
the roadway widths, shoulders (or lack
thereof), alignment, or other features
with regard to the roads themselves in its
Traffic Assessment Report. The applicant
has no duty under law to construct
off-site improvements. If the roads are
not sufficient to handle the additional
12,000 trips per day (and it is likely
that they will not be able to handle this
increased traffic), there is no mechanism
in place to assure the safety of persons
using the roads.
- The traffic
volumes included anticipated traffic from
the adjoining project, the Liberty Estates
subdivision, based on the gravity model
population centers.
- The Traffic
Assessment Report submitted with the
proposed PRD, was also submitted to
PennDOT to determine whether the scope of
the study was sufficient. As of the time
of the hearing, PennDOT had not indicated
it position on the sufficiency of the
scope of the study.
- The applicant
submitted, as part of the Supplemental
Data, a Water Feasibility Study prepared
by Thomas Waddington, P.G., concluded
that, based on his studies, there are
sufficient groundwater resources available
for the proposed communities (Liberty
Valley PRD and Liberty Estates), as well
as for the existing population in the
study area.
- The Water
Feasibility Study estimates average water
usage per residential unit of 200 gallons
per day and maximum demands of around 300
gallons per day. The commercial use per
business (24 businesses total) would
average around 800 gallons per day and
commercial maximum demand would be 1200
gallons per day.
- The Water
Feasibility Study clearly states that the
"maximum daily demands" for residential
and commercial use of 425,000 GPD.
- The Water
Feasibility Study reported on the drilling
of two test wells. One of the test wells
was drilled to a depth of 220 feet and
yielded 600 gallons per minute (estimated
through the bucket and stopwatch methods).
The other test well was drilled to a depth
of 300 feet, and yielded 800 gallons per
minute (by the same methods). Either well
could meet the demands of the PRD.
- The applicant
will be required to obtain a public water
supply permit from the PaDEP, which will
review water quality issues and available
water supply issues in the community.
- The Water
Feasibility Study indicates that a storage
tank of adequate size will be included in
the system to supply water for operating
emergency and fire reserve capacity.
- The application
fails to identify the size or location of
the water storage tank, which will
probably be approximately 150 feet in
height.
- The Natural
Features Analysis within the Supplementary
Data identified the existing locations and
types of vegetation found within the
project area including the delineation on
the tentative plan of mature tree areas,
wetlands and flood plains.
- The applicant's
Community Impact Analysis submitted with
the tentative plan includes the
applicant's projection of potential
impacts of the proposed Liberty Valley PRD
on various municipal services and public
facilities, including the Fairfield Area
School District, Liberty Township and the
Fire and Emergency Management Services
that provide services to the Township.
- A Community
Impact Analysis was submitted based upon
the Penn State model to estimate the
impact of the Liberty Valley PRD, both
separately and in conjunction with the
proposed Liberty Estates subdivision upon
municipal services including the impact on
the Fairfield Area School District.
- Applicant
presented testimony that the proposed
Liberty Valley PRD would be self
sufficient in that the Owners Association
would be responsible for maintenance of
the equestrian center and clubhouse and
the provision of the maintenance of parks
and common areas to the extent that such
facilities are not accepted by the
Township. Testimony also indicated that no
public or municipal impact would result
from utility services since water supply
and sanitary sewage collection and
treatment would be provided by a public
utility corporation or by the Owners
Association.
- Applicant's
expert estimated that the Liberty Valley
PRD will generate approximately 2,233 new
residents once the project is completely
built out in 2021, which total would
include approximately 381 new school age
students for the Fairfield Area School
District. These numbers are based on
census data for persons per unit in a
similar project developed by an affiliate
of the applicant (Worman's Mills in
Frederick, Maryland) and census data
applicable to existing school populations
within Liberty Township. Applicant
believes that this data was supported in
the applicant's experience in The Links at
Gettysburg, Mount Joy Township,
Pennsylvania.
- Using the Penn
State model, the applicant determined the
cost and financial impacts of the Liberty
Valley PRD and the Liberty Estates
subdivision on the Fairfield Area School
District and concluded that the school
district can expect a net positive impact
of approximately $2.9 million. However,
the Penn State model is not appropriate,
by its own terms, to situations where new
schools or expansions of schools will be
needed to meet the needs of the new
development.
- It was also
estimated by applicant, using the Penn
State model, that the cost and financial
impacts of the Liberty Valley PRD and
Liberty Estates subdivision on the
Township and determined that the Township
would experience a net positive impact of
$565,000. However, this estimate used the
existing budget for the Township which had
no monies devoted to "road repair" or
"road construction" and reconstruction due
to an overrun during a previous budget
year. Therefore, the estimate was not
based upon a normal budget year and
underestimated the per capita cost per
resident. Regardless, the Penn State model
is not appropriate, by its own terms,
where road expansion is required to meet
the needs of the development.
- The applicant
reviewed the existing fire call volumes of
the Fairfield Fire Company and concluded
that the Liberty Valley PRD and the
proposed Liberty Estates subdivision would
add approximately 78 new fire calls per
year once the project is completely built
out in 2021.
- The applicant
prepared a response time analysis,
supported by an independent GIS analysis,
which concluded that response times for
emergency vehicles from Fairfield or
Emmitsburg, MD, to the Liberty Valley PRD
would be approximately 10 to 15 minutes.
- Mr. Koch, one of
applicant's expert witnesses, testified
that the applicant was willing to
contribute $250.00 to the Fairfield Fire
Company for each unit sold within the
Liberty Valley PRD at the time of closing
on the unit, which would provide
approximately $295,250 to the Fairfield
Fire Company upon the sale of all units.
The donation of land and that sum of money
is inadequate to establish a satellite
fire station at the project site.
- The applicant
offered a one acre lot within the Liberty
Valley PRD to the Fairfield Fire Company
where a new fire substation could be
constructed to serve the surrounding area.
- The applicant
studied the existing police services in
the Township and concluded that the
Township will need to add two full time
police officers over the life of the
project and that the additional tax
support of $140,212 from the project will
cover the additional costs of expanding
the Liberty Township Police Department.
- The Tentative
plan identifies areas of common open space
including trails and parks that are
located through the Liberty Valley PRD.
- The common open
space areas have been designed, where
possible, to incorporate significant
natural features within the project area.
- The applicant
contends it has provided 44.7 acres of
proposed active recreation area or 37.9%
of the proposed common open space. The
common open space includes a recreational
park with what appears to be a baseball
field, two unidentified fields, the
equestrian center, trails, and pocket
parks. See, Discussion, below, concerning
the common open space.
- The applicant has
represented that improvements identified
in Section 5.5(D) [streets, sewer and
water utilities, storm drainage and soil
erosion control, curbs and gutters, and
sidewalks] will be designed and improved
in accordance with the applicable
requirements of the Subdivision and Land
Development Ordinance.
- The applicant has
represented that off-street parking and
loading facilities will be designed in the
final plans for each phase in accordance
with Sections 6.5 and 6.6 of the Zoning
Ordinance.
- As identified on
the Tentative plan, all telephone,
electric, and cable television utilities
are proposed to be installed underground.
- The applicant has
identified areas of mature trees where
existing trees are greater than six inches
in diameter and has submitted a
landscaping sketch with the Tentative plan
submission. The landscaping sketch fails
to show any landscaping for the parking
areas around the commercial buildings.
- The applicant has
represented that the Owners Association
shall own and maintain any common open
space, including any common open space
offered to the Township for dedication,
but not accepted by the Township.
- The Liberty
Valley PRD is proposed to be developed in
phases starting in January of 2005.
- The Tentative
plan includes a phasing schedule that
identifies the location and approximate
time of construction of each phase of the
project. More than fifteen (15%) percent
of the proposed residential units in the
Liberty Valley PRD are included in the
first phase as shown in the Phasing
Schedule in the Addendum to Supplementary
Data.
- The commercial
area of the Liberty Valley PRD is proposed
for the last phase, Phase 10, which phase
does not include any residential units.
The result is that the residents will not
be served at the project site until
sometime after 2016, compounding the
traffic on the roads as the residents
drive to Fairfield, Emmitsburg, and/or
Gettysburg for their every need.
- Horseback riding,
walking, and fast walking can be
considered active recreation, and areas
designated for these uses within the
proposed Liberty Valley PRD can be
included as active recreation open space.
Horseback riding is not an appropriate
activity on the same trails used for
walking and fast walking. The use of a
trail for horseback riding, in effect,
makes that trail a single use trail. See,
Discussion below.
- The President of
the Fairfield Fire Company testified that
the Township should consider an ordinance
requiring that condominium dwellings
within the proposed Liberty Valley PRD be
equipped with sprinkler systems. He
indicated Fairfield Fire Company is not
currently equipped to handle fires in a
multi-unit dwelling.
- The applicant
will have to obtain permission from state
and/or federal authorities to perform
construction in the wetlands.
- Replacing
encroached wetlands with substitute
wetlands does not cure the alteration made
to the site. Encroaching in the wetlands
will cause a permanent and undesirable
change to the site.
- Tract Road has
been classified in the Comprehensive Plan
in the Township's possession as an
"Arterial" street. Efforts were made in
1992 to have Tract Road classified as a
"major collector" street in the
Comprehensive Plan. Whether it is
classified as an Arterial or Major
Collector street, Tract Road is a major
street for the purposes of the Liberty
Township Zoning Ordinance and the Liberty
Township Subdivision and Land Development
Ordinance.
- A "major street"
is defined in Section 704 of the
Subdivision Ordinance as: "A street
serving a large volume of comparatively
high speed and long distance traffic,
including all facilities classified as
main and secondary highways by the
Pennsylvania Department of
Transportation." Subdivision Ordinance,
Section 704.
- Tract Road, in
comparison with all of the other roads and
streets in Liberty Township (including Pa.
Route 16) is a high speed and long
distance road.
- By custom and
past practice, and for reasons of safety,
the distance between access drives and
intersections are to be measured from the
edge of a cartway of a street or road
intersection to the edge of an access
drive.
- The distances
between some of the access drives to the
commercial area and the nearest
intersections are less than the 50 feet
required by the ZO, §6.5.E. made
applicable to PRDs by §5.5.E.
- The application
shows sufficient parking area provided for
multi-family residential buildings, but no
visitor parking has been provided.
- The applicant
expects than less than one-quarter of the
inhabitants of the PRD will engage in the
primary active recreation that is planned,
being equestrian activities.
- If 15% of the
inhabitants of the PRD engaged in the
activities planned by the applicant, one
expert believes that 50 horses would be
needed. (The Board, using the figures
presented by the expert, calculates that
the correct number would be 20 horses,
assuming all horses are healthy. It is
expected that 20% of the horses would be
unavailable at any given time due to
lameness or sickness. Therefore, at least
24 horses would be needed.)
- The amount of
space set aside for equestrian activities
is insufficient to house and care for the
number of horses (be it 20 or 50) required
to provide the activities planned by the
applicant..
- The applicant has
made an offer on the record that it would
accept a condition with respect to
existing wells that, if a fair procedure
is available to determine that any
impairment is caused by the wells to be
developed for the Liberty Valley PRD, that
the applicant will either pay for the cost
of improvement of the affected person's
well or connect the person to the water
system without cost, upon the
understanding that once the person is
connected he would have to pay for the
water service.
III. CONCLUSIONS OF
LAW 1.The burden is on the applicant to
prove that the application meets all of the
requirements of the ZO and of the MPC. 2.The
burden is on the applicant to identify any
and all required modifications to the
municipal land use regulations otherwise
applicable to the subject property. 3. The
Liberty Township Subdivision and Land
Development Ordinance is applicable to
planned residential developments. 4. The
applicant must meet all SALDO requirements
by the final plan stage unless modification
has been requested and granted. 5.At the
time the Liberty Valley PRD application was
filed with the Township planned residential
developments were not permitted in Liberty
Township. (See discussion in Introduction
concerning the proceedings held on this
application in the event that a final order
of court ruled that PRDs had not been
removed from the ZO in 1985.) 6.The proposed
Liberty Valley PRD does not comply with all
of the planned residential development
provisions set forth in Article V of the
Zoning Ordinance. 7.The proposed Liberty
Valley PRD is not consistent with the goals
of the Liberty Township Comprehensive Plan.
8.In addition to the failure of the
application to meet all of the requirements
of the ZO, there are particular deficiencies
with the application that militate against
the public interest. 9.The application shows
that the proposed PRD is not beneficial to
the neighborhood surrounding the site of its
proposed location (see Findings of Fact, and
Discussion).
IV. DISCUSSION
This Discussion
section may contain facts which, by
oversight, were not stated in the Findings
of Fact. If facts are contained in the
Discussion that are not part of the Findings
of Fact, then those facts should be deemed
to have been included in the Findings of
Fact section of this Decision.
A. Lack of
Consistency with the Liberty Township
Comprehensive Plan.
Section 709 of the
MPC requires that any decision on a
tentative plan application include findings
of fact and conclusions on those respects in
which the application is or is not
consistent with the township's comprehensive
plan.
1. Agricultural
Preservation. The Comprehensive Plan of
Liberty Township in pages 7 through 10 of
Phase 2 sets out an "Agricultural Land Use
Plan". It identifies certain areas of the
Township that have good agricultural soils,
but due to their location near existing
residential populations and the likelihood
of public utilities extensions, are not
recommended for agricultural preservation.
Other areas are identified as locations in
the Township were agricultural preservation
should be pursued. An Agricultural Land Use
Plan map is included in the Comprehensive
Plan on page 10. The applicant's proposed
development falls completely within an area
marked on the said map as a location for
agricultural preservation. The location of
the proposed PRD in this area conflicts with
the Comprehensive Plan and is not consistent
with it.
2. Residential Land
Use Plan. Pages 17 through 20 of Phase 2 of
the Comprehensive Plan discusses those areas
of the Township that are most suited to
increased residential development. Page 19
is a map showing the Residential Land Use
Plan, including areas where future
residential development would be best
suited. "The policy of the Comprehensive
Plan is to retain the general character of
the Township as one primarily devoted to an
agricultural and residential community.
"This policy is to be implemented through
the limitation of mass residential
development to the ample vacant land in and
near the already developed portions of the
Township, and in close proximity to feasible
future public utilities. The best suited
agricultural lands will be reserved for such
use, and any residential development in
these areas will be of a relatively low
density."
Liberty Township
Comprehensive Plan, Phase 2, page 17.
The applicant's
development falls completely outside of the
areas identified on the said map as
locations for future residential
development. The location of the proposed
PRD conflicts with the Comprehensive Plan
and is not consistent with it.
3. Street
Classification. Phase 2 of the Comprehensive
Plan contains a classification of the roads
in Liberty Township. This classification
system is expressly stated to be the same
classifications as contained in Phase 1 of
the Comprehensive Plan. Liberty Township
Comprehensive Plan, Phase 2, page 351. The
applicant's proposed development lies on the
east and west sides of Tract Road. It also
lies on the north and south sides of
Wenschof Road, and on the north side of Crum
Road. The Township's version of the
Comprehensive Plan identifies Wenschof Road
and Crum Road as "collector" roads, and
identifies Tract Road as an "arterial" road.
In Phase 1 of the Comprehensive Plan,
Collector Roads are stated to "transport
primarily local traffic between arterial
roads and the minor streets and roads
throughout the Township." Arterial Roads
"generally carry significant traffic volumes
between neighboring communities or within
the Township." Tract Road begins in the
Borough of Fairfield (labeled as both
McGinley Drive and Tract Road in the
Borough), and traverses Hamiltonban Township
and Liberty Townships to its terminus south
of the Mason-Dixon Line on Maryland Route
140 just outside Emmitsburg, Maryland. It is
a main highway from the Fairfield area to
the Emmitsburg area. The applicant has
treated Tract Road as a collector road. The
Township finds that Tract Road is either an
Arterial road, or a "major collector" road
for the purposes of designing developments
in the Township. The classification of Tract
Road as something less than a "major" street
by the applicant is not consistent with the
Comprehensive Plan (nor the SALDO).
. B. The extent to
which the application departs from zoning
and subdivision regulations otherwise
applicable to the property, and the reasons
why such departures are or are not deemed to
be in the public interest are to be included
in the decision. MPC, §709(b)(3).
Two witnesses have
demonstrated that many of the SALDO
requirements for plans have not been
complied with in the application. The Board
concurs that the application does not
demonstrate that many of these requirements
have been, or will be met. However, it is
the position of the Board that if the
applicant has not requested a modification
of otherwise applicable land use
regulations, then it is expected that if
there is a final plan stage those
requirements will be met or the final plan
will be denied. See, I. Background, B.
Interplay between the Municipalities
Planning Code and the ZO, above.
1. Distance of some
townhouses from streets. Section 5.5(A)(5)
of Article V of the ZO, Planned Residential
Developments, directs that all structures
should be no less than 20 feet from the
right of way of collector streets. The
application shows that this requirement has
not been faithfully observed by some of the
townhouse units. The failure to comply with
this requirement is an encroachment into
what are to be open pathways in areas where
dense development is already provided in a
PRD, and is unwarranted. This violation
negatively affects the public interest as it
removes one of the very few aspects of
openness in the densely developed area, and
limits the area for stock piling of plowed
snow and for potential future widening of
the street.
2. Location of
parking stalls. Section 6.5 I. of the ZO
requires that all parking stalls shall be no
less than 10 feet from principal structures.
The application shows that certain stalls in
the commercial area violate this
requirement. This violation of the ZO is not
substantial and could be easily corrected at
the final plan stage by removing those
spaces.
3. Bridge and
culvert design. SALDO §302.2.d requires
designs of bridges and culverts. The
applicant had requested a modification so
that these designs would not be required
until final plans are submitted. In the
Addendum to Supplementary Data, culvert
designs were provided. The Board questions
whether, pursuant to MPC §707(b) such
designs were required at the tentative plan
stage. However, if such plans would be
deemed to be required at the time of
submission of a tentative plan, and such
designs have not already been submitted,
then a modification is granted to allow them
to be submitted at the final plan stage.
4. Erosion and
sedimentation plan. SALDO §302.2.i requires
that an erosion and sedimentation plan,
together with a letter from the Department
of Environmental Protection acknowledging
the adequacy of the plan, be submitted. The
applicant seeks a modification of that
requirement at the tentative plan stage. The
Board questions whether, pursuant to MPC
§707(b) such designs are required at the
tentative plan stage. However, if such plans
would be deemed to be required at the time
of submission of a tentative plan, a
modification is granted to allow them to be
submitted for the first time at final plan
stage.
5 Minimum length of
blocks. SALDO §403.2.a requires that blocks
have a minimum length of 500 feet. Several
blocks in the applicant's submission do not
meet that minimum requirement. The length
and location of blocks is important to
demonstrate the bulk and location of
structures, as contemplated by MPC
§707(b)(iv). No modification of this
requirement has been formally requested. The
Board finds that the provision of blocks no
less than 500 feet in length helps to
prevent the proliferation of intersections
too close to each other, which can be a
traffic hazard. As there was no request for
relief from this requirement based upon the
topography or storm water run off concerns,
the reason for minimum block lengths remains
in tact. As a safety issue, the public
interest would be affected by an allowance
of short blocks, and the plan does not
conform with SALDO.
6. Clear sight
triangles. SALDO §402.9.a. requires that
clear sight triangles be shown on plans to
assure that adequate vision is available to
vehicles entering a road way at an
intersection. In the case of roads other
than "major" streets, the clear sight
triangle must be 75 feet from the point of
intersection of the centerlines of the roads
in question. The clear sight triangles for
"major" streets must be 150 feet. The
applicant's plan shows that at several
intersections along Tract Road, the 150 foot
clear sight triangle is obstructed by
townhouse units. Although the applicant
believes that Tract Road is not a "major"
street, the Board has concluded that based
upon the Comprehensive Plan classification
(in Phase 1 and in Phase 2), and the
definition found in SALDO, Tract Road is the
major road in the Township, other than Route
16. As a result, the plan does not conform
to SALDO. The failure to comply with the
requirement presents a vehicular safety
hazard, and affects the public interest.
7. Proximity of
intersections to one another. SALDO
§402.8.d. requires that intersections with
"major streets" shall be not less than 1,000
feet apart (as measured from the centerline
of one intersection to the centerline of the
next intersection, where those centerlines
intersect the major road's centerline).
Several of the intersecting roads from the
proposed PRD do not meet this 1,000 foot
separation distance. As above, the
requirement of the 1,000 foot distance is
applicable because of Tract Road being a
"major" road. The plan does not conform to
SALDO. The failure to comply with the
requirement presents a vehicular safety
hazard, and affects the public interest.
8. Service alley
width. SALDO §402.3 requires that alleys be
24 feet wide, with the cartway using the
entire right of way width. The applicant has
requested a modification of this
requirement, so that the right of way for
the alley would be 16 feet, and the cartway
of the alley would be 12 feet. Since the
alleys provide access to very densely
developed residential units, it is important
that they be assured of being open in all
types of weather. With a 24 foot width,
there is the assurance that plowed snow can
be stored to the sides of the alleys, and
emergency vehicles could still have access
to the properties served by the alley from
the alley side. If the alleys are narrowed
as requested, it is likely that they could
be shut for periods of time during the more
significant snow falls experienced in this
area, which in turn could block access by
fire fighting and other emergency equipment.
There are many townhouses that are designed
to front on Tract Road. Because Tract Road
is a major, but narrow, road in the
Township, parking on it is not an option.
This necessitates a more usable service
alley in the back, since moving vans and
other delivery vehicles will not have the
option of any access from the front.
Therefore, the modification is denied, and
the plan as presently drawn is not in
compliance with SALDO. As this noncompliance
could seriously hinder emergency equipment
access, it negatively affects the public
interest.
9. Length of
cul-de-sac streets. SALDO §402.10.(c) limits
the length of permanent cul-de-sac streets
to 500 feet. The applicant is requesting
that the maximum length be permitted to be
800 feet for this proposed PRD. The Board
finds that because cul-de-sac streets allow
the denser development envisioned in a PRD
without having to design through streets
(which would become more heavily traveled),
the extension of a cul-de-sac street length
to 800 feet would serve the public interest
and the purposes of a PRD. The modification
requested by the applicant is granted as
shown on the tentative plan submitted.
10. Set back of
garages from alley. SALDO §402.12.b.
provides that structures shall not be
located closer than 10 feet to the right of
way of a "service street", sometimes known
as an alley. The Board believes that this
set back requirement serves an important
function, together with the required width
of the service street right of way, in
providing a place for plowed snow storage,
and access by service and emergency
vehicles. The modification requested in the
application is denied. The adherence to the
requirements of the SALDO is deemed be in
the public interest.
11. Sheet Size (of
the plan paper) and Key Map Scale. The
applicant requested modifications from the
size of the paper on which the plan was to
be presented, and the scale of the key map.
These requested modifications are granted.
C. The purpose,
location and amount of the common open space
in the project, the reliability of proposals
for maintenance and conservation of the open
space, and the adequacy or inadequacy of the
amount and purpose of the common open space
as related to the proposed density and type
of residential development.
1. Common Open Space
and Active Recreation Area. The ZO requires
that a PRD set aside no less that 25% of the
total site area for "common open space". ZO,
§5.3.C.2. "Common open space" is defined as
follows:
Common Open Space: A
parcel of parcels of land or an area of
water, or a combination of land and water
within a development site and designed and
intended for the use or enjoyment of
residents of the particular development, not
including streets, off-street parking areas
and areas set aside for public facilities.
Common open space shall be substantially
free of structures but may contain such
improvements as are in the development plan
as finally approved and as are appropriate
for the recreation of the residents.
ZO, §12.1.22.
The ZO also requires
that no less than 25% of the total common
open space area shall be suitable for
"intensive use as an active recreation
area". ZO, §5.5.C.2. There is no definition
in the ZO for "active recreation area",
although there is a definition for "active
play area". The two do not appear to be
synonymous. The application indicates in
notes that the total acreage of the site is
444.70, and that 118 acres will be devoted
to "open space". The acreage devoted to open
space, then, is reported to be 26.5% of the
total site acreage, or 1.5% more than
required by the ZO. That 1.5% equals 6.7
acres. There was no testimony regarding the
exact area of common open space that is used
for stormwater management ponds or basins.
Storm water detention basins are deemed to
be "public facilities". This conclusion is
evidenced by the requirement that they must
be either constructed prior to the signing
of a subdivision or land development plan,
or they must be assured by financial
security prior to the signing of an approved
plan. See, MPC §509(a). By definition,
common open space does not include public
facilities, such as storm water facilities.
Without any proof that the area of the storm
water management ponds or basins shown on
the application is less than 6.7 acres,
there has been a lack of proof that the
minimum area required for "common open
space" has been set aside. The application
also reports that the active recreation area
has been met because 44.7 acres of land are
set aside for such use. That is reported to
be 37.9% of the common open space. Assuming
that the report is correct, the amount of
acreage set aside for active recreation
exceeds that required by the ZO. (Twenty
five percent of the required open space,
which is 25% of the total site, is in effect
6.25% of the total site acreage. Multiplying
the total site of 444.79 acres times 6.25%
means that 27.79 acres must be devoted to
active recreation area. The reported acreage
exceeds this.)
2. Reliability of
proposals for maintenance and conservation
of the open space. The applicant indicated
that the common open space will be
maintained and conserved by fees charged to
the residents of the development (both
homeowner association fees and user fees for
those who avail themselves of the equestrian
facilities). In the alternative, those areas
will be maintained by the said fees and by
tax dollars should the Township choose to
accept some or all of the common open space
that is dedicated to the Township. (It was
repeatedly acknowledged by counsel for the
applicant that the Township did not have to
accept any of the dedications, and if it did
not, the residents through their homeowners
association would have to pay all of the
costs of maintenance and upkeep of common
areas. See also, Liberty Valley Tentative
Plan Supplementary Data, 3. Supporting Data,
COMMON SPACE, (page not numbered).) There
was testimony from an expert witness
presented by protestants that the proposed
equestrian facilities, as reasonably
inferred from the application, could not
financially sustain themselves based upon
the activities to be provided and the fees
suggested by a "comparable" equestrian
facility. See, Liberty Valley Tentative Plan
Supplementary Data, Market & Feasibility
Analysis, Equestrian Community Comparable:
Summerfield in Chester County, PA, (page not
numbered).
The idea of an
equestrian oriented community has appeal,
but does not appear to have been properly
analyzed with regard to on-going maintenance
and conservation of common open space. As
the expert pointed out, the amount of money
to be generated by the equestrian facilities
does not come close to maintaining the
equestrian facilities themselves, let alone
the damage that will be done to the common
open space by the keeping of more horses
than the land can accommodate. The result is
that there is no reliability in the
application that common open space, and its
included active recreation area, will be
preserved and maintained.
Although the
application states that the common open
space owned by the association "will be
maintained solely from funds collected from
the owner's [sic] association assessment
fees", the representations made at the
hearing were that both assessment fees and
user fees would be collected. It was
inferred that the equestrian facilities
expenses would be met by the fees collected
from the active users, and not from the
assessment of the residents (with the
possible exception of the clubhouse). Based
upon those representations, and the logical
inferences from them, the maintenance and
conservation of the common open space
available to equestrian use is not assured.
3. Adequacy of the
amount and purpose of common open space. As
discussed above, the amount of common open
space has not been met.
The purpose of the
common open space is twofold: to have open
space for the enjoyment of the residents;
and, to provide active recreation for the
residents. With regard to the latter, an
area is shown in the application on Sheet 6
of 32 for three fields, one of which gives
the appearance of a soft ball or baseball
field, and the others are undefined. Other
parts of the submission show trails that are
to serve as equestrian trails and as
walking/hiking trails. The number of
residents expected to participate in
equestrian activities is estimated to be
less than 25%. No estimate was given, nor
was any evidence offered, for the number of
residents expected to use the trails and the
recreation fields. While the idea of an
equestrian oriented community has surface
appeal, it is apparent that such facilities
fall far short of meeting the needs of the
approximately 2,233 residents that applicant
says will live in the PRD. The applicant
states in its application that it expects
less than 25% of the population to use the
equestrian facilities. The expert produced
by protestants has indicated that the areas
currently shown on the application for
equestrian purposes may not be sufficient to
provide the equestrian activities for even
15% of the population. In addition, no
matter how many people use the trails for
horse related activities, that use makes
those trails unappealing, if not unusable,
for other active recreation such as walking,
jogging and hiking. The churning effect of
horse hooves, together with the inevitable
manure, are not conducive to other
activities at the same location.
With more than 75%
per cent of the residents wanting something
other than horse related activities for
active recreation, there will be
approximately 1,6752 or more people who will
have only the three recreation fields in the
project to meet that need. Clearly, the plan
does not come close to providing facilities
to meet the active recreation needs of the
community because such a large amount of the
active recreation area is devoted to use by
a relatively small number of residents. The
purpose of having 25% of the common open
space devoted to active recreation is
defeated by the primacy given to the
equestrian activities.
D. The physical
design of the plan, and the manner in which
the design does or does not make adequate
provision for: public services; control over
traffic; the furtherance of the amenities of
light, air, recreation and visual enjoyment.
1. General comments
on the design. The physical design of the
project has serious flaws that militate
against the essential nature of a PRD. The
project area has been aptly described as a
serpentine layout. That layout makes the
creation of a centralized community
impossible.
The design also has
created an extensive border, larger than
that which would have existed had the
development site been more of a rectangle or
a circle. The result is that the opportunity
for increased conflicts with neighboring
agricultural uses is vastly increased.
The project has been
designed to lie on both sides of Tract Road,
a major road in the Township. Residences lie
on both sides of Tract Road, as do
recreational facilities. The equestrian
facilities lie on the western side of Tract
Road, while the recreation fields lie on the
east side. This means that residents will be
crossing Tract Road frequently, depending on
where they live and which recreation they
choose to pursue. The Board does not believe
that the location of a major road in the
middle of what is supposed to be centralized
community is a good design. It presents
significant safety hazards to pedestrians,
and will encourage overuse of motor vehicles
to travel from one side of the project to
the other.
The design also
places numerous townhouses in places where
convenient access to pocket parks and other
passive recreation activities is
inconvenient. See, for example, townhouses
in Phase 1C. The lots in Phase 3 are all
located at great distance from any usable
active recreational spaces and any pocket
parks.
The design includes
several townhouses fronting on Tract Road.
See, lots 52 through 81 in Phase 5. Since
Tract Road is a major, but relatively narrow
road, parking on Tract Road is not
anticipated, in the interest of health and
safety. The result is that those townhouses
have no place for guest parking. So, too,
throughout the project, there are no places
provided for guests to park except on the
streets.
The project's design
also places many homes in identified
wetlands. See, lots 1 through 4, 15 through
19, 105 and 106 in Phase 3. Although there
are procedures available to substitute
created wetlands for natural wetlands, the
Board finds that such substitutions are not
as desirable as retaining natural wetlands.
The Board further finds that it is against
the public interest to place residential
lots in wetlands.
The project is also
designed to place a significant portion of
the trail system around the perimeter of the
site. Since these trails are intended for
equestrian use, this design creates an
increased risk of conflict with neighboring
properties unless a fence is built to
enclose the trails. Such a fence is not
shown in the application.
2. Comments on the
design as it affects public services. As
required by the ZO, the proposed project
will have community sewer and water systems.
At the tentative plan stage, there is little
to review regarding these community systems.
It is understood that community sewage and
water systems must be approved and permits
granted for them by the Pennsylvania
Department of Environmental Protection.
The water system,
however, will require storage for emergency
use and for pressure. One witness estimated
that approximately 300,000 gallons of water
will need to be stored. He also testified
that a tank for such storage, to create
pressure, would have to be approximately 150
feet in height. There was no contradictory
evidence on this matter from the applicant.
A structure of this size would be
substantial, and its location should be
known. Unless residences were to be removed,
the only place that a structure of this size
could be placed would be in areas now
reserved as common open space. The amount of
common open space has not been shown to be
sufficient (see, Discussion above) and the
placement of a water tank in that common
open space would diminish it further.
3. Design affecting
traffic. The design of the proposed project
is inimical to traffic flow and safety.
There are numerous entrances onto Tract Road
in the design. These intersections have the
effect of treating Tract Road, a major road,
as just one more minor street in the
development. Clear sight distances required
for intersections at major roads are not
provided. Many commercial parking spaces
will interfere, since cars parked in those
spaces will block the line of sight. In
other locations, townhouses are to be built
in the area required to be reserved for
clear sight.
The design also
fails to show that any consideration has
been given to the existing road conditions.
The traffic information submitted by the
applicant concentrates on existing
intersections in and around the project
site. No information was provided whether
the roads in between those intersections can
handle the substantial increase in traffic
that this development will generate. Section
5.4.B. of the ZO requires that an analysis
of the "roadway systems" be conducted. The
Board finds that the term "roadway systems"
is not limited to intersections.
4. Design effects on
light, air, visual enjoyment, and
recreation. The commercial parking lot is a
visual blight from Tract Road, and for all
of the residences that front towards the
commercial center. This blight could have
been avoided if housing was planned around
the commercial parking so that the rear of
the residences, and the service alleys
behind those residences, backed up to
parking lots. This would have been superior
to having residences front on open parking
lots. The sight of a150 foot water tower in
the middle of the valley will certainly be
an eyesore to many. The magnitude of this
visual intrusion is unknown as the tentative
plan does not show the location of the water
tower, nor the applicant's estimate of its
size. The effect on wildlife and the
enjoyment associated with spotting birds and
other wildlife is something that will be
affected as construction is planned for
identified wetland areas. An abutting
neighbor is enrolled in the Conservation
Reserve Enhancement Program which, among
many conservation oriented objectives, is
intended to provide cover for birds and
other mammals. This area is dependent upon
the continued environmental conditions
presently there. The removal of wetlands may
affect the conservation area on the
neighbor's land. The lack of proper
recreation in the design has been discussed
above, and is incorporated herein by
reference. The primary recreation facility
will not be built until seven years after
the beginning of the project's construction
and 781 homes have either been built or are
under construction. Therefore, the primary
active recreational use will not serve a
significant portion of the project's
population, and will not serve any of its
population for years after the project is
commenced. This inadequacy and delay will
strain the other recreational opportunities
in the area.
E. The relationship,
beneficial or adverse, of the proposed PRD
to the neighborhood in which is it is
proposed to be established. The proposed PRD
puts residential uses in the middle of an
existing agricultural and low density area
of the Township. It proposes, as it must,
centralized water and sewer systems. The
Comprehensive Plan recognized that such
systems should not be promoted in the
agricultural areas of the Township as those
systems encourage other development. In
fact, the proposed PRD is doing just that,
since this applicant is also proposing a 106
home subdivision that will utilize the
centralized water and sewer systems in the
PRD. This relationship is not beneficial to
the neighborhood. However, the GU district
permits single family dwellings on 1 acre
lots, and the AR district allows single
family dwellings on 2 acre lots. While the
proposed PRD is denser than those district
regulations, the affect of the PRD on the
neighboring uses is only different from the
permitted-by-right housing in degree.
F. The sufficiency
of the terms and conditions intended to
protect the interests of the public and the
residents, with regard to the integrity of
the plan, when it is built in phases.
The applicant
submitted in the Amended Supplementary Data
a form of use restrictions that will be
imposed upon all purchasers in the proposed
PRD. The applicant has also shown that a
home owners' association corporation has
been formed. There was no evidence to
indicate that the protections contemplated
by MPC §709.B.(6) would not be sufficient.
V. DECISION
The application of
Liberty Valley Development Company, LLC, for
tentative plan approval for the Liberty
Valley planned residential development is
hereby denied.
Read other articles related to Fairfield